Bitte verwenden Sie diesen Link, um diese Publikation zu zitieren, oder auf sie als Internetquelle zu verweisen: https://hdl.handle.net/10419/53611 
Kompletter Metadatensatz
DublinCore-FeldWertSprache
dc.contributor.authorJayasuriya, Sisiraen
dc.contributor.authorMcCawley, Peteren
dc.date.accessioned2010-01-03-
dc.date.accessioned2011-12-15T12:25:52Z-
dc.date.available2011-12-15T12:25:52Z-
dc.date.issued2008-
dc.identifier.urihttp://hdl.handle.net/10419/53611-
dc.description.abstractThis paper examines several aspects of the rehabilitation and reconstruction program that followed the 2004 tsunami in Asia. Almost 230,000 people died in the disaster. We focus on two main issues: aid delivery and reconstruction policy following the disaster. Although issues such as immediate relief activities in disaster management and the role of political, institutional, and social factors in post-disaster recovery are also very important, they are not discussed in detail here. First, the effectiveness and financing of aid delivery arrangements following the tsunami are considered. The discussion aims to go beyond the headline figures on international aid to assess the level, composition, and quality of aid flows. Second, the challenges of designing reconstruction programs in the wake of the tsunami are surveyed. Questions of why there is often sharp escalation in construction costs and the implications for planning reconstruction are considered. These issues are often not discussed in the standard analytical literature about responses to disasters. It is argued that staggered disbursement of aid funds, although obviously highly undesirable in the case of urgent relief activities, may have benefits during the reconstruction phase by reducing inflationary pressures and leakage of aid funds. The pros and cons of alternative approaches are considered. Finally, it is suggested that a phased reconstruction program where the sequencing of activities is carefully prioritized will deliver better outcomes.en
dc.language.isoengen
dc.publisher|aAsian Development Bank Institute (ADBI) |cTokyoen
dc.relation.ispartofseries|aADBI Working Paper |x125en
dc.subject.jelF35en
dc.subject.jelH54en
dc.subject.jelO19en
dc.subject.jelQ54en
dc.subject.ddc330en
dc.titleReconstruction after a major disaster: Lessons from the post-Tsunami experience in Indonesia, Sri Lanka, and Thailand-
dc.typeWorking Paperen
dc.identifier.ppn604630115en
dc.rightshttp://www.econstor.eu/dspace/Nutzungsbedingungenen

Datei(en):
Datei
Größe
151.97 kB





Publikationen in EconStor sind urheberrechtlich geschützt.